EXCERPT FROM REFERENCES

Plant servicing
Lenzing AG
Lenzing (AT)
Routine repair and maintenance
Routine repair and maintenance works at the boiler plant and the
auxiliary plant, economizers, reheaters, superheaters, membrane
walls, headers, HP-pipes.
ENBW Kraftwerke AG
CHP Heilbronn (DE)
Routine boiler maintenance
Routine boiler maintenance at superheaters, headers, flue gas ducts,
catalysts, economizers and air preheaters.
Mondi Packaging
Frantschach (AT)
Routine repair and maintenance
Routine repair and maintenance works at the boiler plant and the
auxiliary plant, economizers, reheaters, superheaters, membrane
walls, headers, HP-pipes, valves, fans, dampers and flue gas ducts.

Annual main revision
Annual main revision in the course of the plant shutdown with up to
150 specialists.
UPM Steyrermühl
Steyrermühl (AT)
Vertical sorter
Replacement of the bearing unit including repair in the FMT workshop.
AVE
Wels (AT)
Routine inspection and repair
Ongoing inspection workings inkluding repair and optimisation at the conveyors.
Smurfit Nettingsdorfer
Nettingsdorf (AT)
SOKE 3 - Recovery boiler retrofit- turnkey erection
Modernisation of a 720 tds/d recovery boiler; dismantling of a bi-drum
boiler system (approx. 350 tons) and installation of a single-drum
natural circulation system (approx. 400 tons). Rebuild during a plant
shut down of 25 days.
Sappi Austria
Gratkorn (AT)
Project "Tiger"
Complete erection of a HRSG boiler with auxiliary firing including steel
structures, piping, stack (height 75 m) behind gas turbine Siemens
SGT-800 (42 MW). Boiler steam m.c.r. 165 t/h, 120 bar, 520°C
voestalpine Stahl
Donawitz (AT)
Blast furnace gas fired boiler plant
Turnkey installation of a boiler island with combined firing including
steel structures, internal and external piping. Quantity: approx.
1775 tons installed; Boiler steam m.c.r. 230t/h, 129 bar, 545°C